Skip to content

Dual feeds, usable kW, dual-corded servers

A+B Power Colocation: What It Means, What It Costs and What to Verify Before You Sign

A+B power means your cabinet gets two independent power feeds, each with its own UPS and distribution path, so a failure or maintenance on one side doesn’t take your servers down. It only works if each feed can carry the whole rack on its own and your servers have two power supplies. A 30A, 208V circuit gives about 5.0 kW of usable power after the 80% rule, so a 5 kW rack needs two of them, not one split in half.

Updated November 2026 · Bob Spiegel, Founder, QuoteColo

The rear of a server cabinet with two rack PDUs, one with blue cords and one with red, feeding servers that each have two power supplies
Bob Spiegel

“Tell me what you’re deploying; I’ll come back with real options from a network built over 20 years.”

— Bob Spiegel, Founder, QuoteColo

From our desk, November 2026

$8,170
two 17 kW cabinets on A/B 60A 208V three-phase, Texas, signed September 2026 (space and power)
$1,732.50
full rack, about 6 kW with A/B feeds and 1 Gbps, Sacramento area, quoted August 2026
$899.30
half cabinet on A/B 120V 20A circuits at 16A maximum, Colorado, closed September 2026
5.0 kW
usable on one 30A, 208V circuit after the 80% rule

From Bob’s signed deals and quotes (customers and providers withheld). Prices are per month.

What A+B power actually is

Your cabinet gets two separate feeds, A and B, that come from independent parts of the facility’s power chain. Not two outlets on one PDU, and not two PDUs from one panel. Two paths that don’t share a component that can fail.

The power chain, and what happens if A and B share a part of it

Part of the chainWhat it doesIf A and B share it
Utility feed and generatorSupplies the power; the generator takes over in a utility outage.One generator that fails to start takes down both feeds.
Transfer switchMoves the load from utility to generator and back.One switch for both sides is a single point of failure.
UPSCarries the load for the seconds until the generator takes over, and cleans up the power.Two PDUs on the same UPS protect you from a PDU failure, not a UPS failure.
Switchboard, panel and breakerCarries power to your row and your cabinet.A and B circuits from the same panel share its upstream breaker.
Rack PDUFeeds your servers’ power supplies.One PDU per side; each must be able to carry the whole rack.

The test: if any single part of the A path fails, does the B path still carry your cabinet? If the answer depends on a shared UPS, panel or generator, it isn’t A+B.

Why A+B power matters for uptime

Power caused 45% of the impactful data center outages Uptime Institute counted in 2025. A+B is the part of the power design that lets maintenance and single failures happen without your servers noticing.

What failed in power-related outages (Uptime Institute, 2026)

  • UPS
    39%
  • Transfer switch
    34%
  • Generator
    28%

Share of power-related outages each part was involved in; one outage can involve more than one. Uptime Institute Annual Outage Analysis 2026 (May 2026).

Maintenance without downtime

With two paths, the facility can service a UPS, a generator or a PDU on one side while the other carries your cabinet. On a single feed, that maintenance means a window with your equipment off.

A failure on one side is an alert, not an outage

A breaker trips at 2 a.m. With dual-corded servers on A and B, the B side carries the load while the A side is fixed. Your monitoring shows a power event; your servers stay up.

Independent generators, not just “backup power”

Facilities have several generators. What matters is whether your A and B feeds draw on different ones, so a single generator fault can’t take out both.

What the Uptime Institute Tiers say about power paths

TierPower designWhat it means for your cabinet
Tier IOne path, no redundant componentsMaintenance needs downtime.
Tier IIOne path, with redundant componentsSome components can be serviced; the path itself can’t.
Tier IIISeveral paths, concurrently maintainableAny part can be serviced without an outage, which assumes dual-corded equipment on A and B.
Tier IVFault tolerantSurvives any single failure as well as maintenance, again with dual-corded equipment.

Uptime Institute removed expected-downtime percentages from its Tier standard in 2009. The 99.671–99.995% figures often quoted come from an older white paper, not the standard. Ask for the Tier certificate itself, and whether it covers the built facility or only its design.

Want these numbers for your own deployment? and we’ll reply with the providers that fit, with their prices.

The 80% rule: what your usable power per feed actually is

A “30A circuit” doesn’t give you 30 amps. Servers run around the clock, which the National Electrical Code treats as a continuous load, so a circuit can only be loaded to 80% of its breaker rating. A 30A breaker gives you 24A.

Usable kW per circuit after the 80% rule

  • 20A, 120VA half rack of light servers
    1.9 kW
  • 20A, 208VA few standard servers
    3.3 kW
  • 30A, 208VA standard full rack
    5.0 kW
  • 30A, 208V three-phaseDense compute and storage
    8.6 kW
  • 60A, 208V three-phaseGPU servers, high-density racks
    17.3 kW
  • 60A, 415V three-phaseThe densest air-cooled GPU racks
    34.5 kW

Volts × amps × 0.8, and × 1.73 for three-phase. That’s apparent power (kVA); modern server power supplies run close to a power factor of 1, so kW is nearly the same. Ask the facility for usable kW per circuit in writing, not the breaker size.

What A+B does to your usable kW

With A+B, each feed must carry your whole rack if the other one fails. Two 30A, 208V circuits give you about 5.0 kW of redundant power, not 10.0 kW. If you load both to 4 kW each, losing one feed puts 8 kW on a circuit built for 5.0, and its breaker trips.

So a rack that draws 8 kW needs each feed sized for 8 kW: a 30A, 208V three-phase circuit (about 8.6 kW usable) on each side. That’s how the Texas deal on our desk was built: two 17 kW cabinets, each on A/B 60A, 208V three-phase circuits, about 17.3 kW usable per feed.

Dual-corded servers: why A+B power only works with the right hardware

A+B at the facility is useless to a server with one power supply. It can only plug into one feed, and when that feed fails, the server goes down whatever the B feed is doing.

HardwarePower suppliesOn A+B
Enterprise 1U–2U servers (e.g. Dell PowerEdge R760, HPE ProLiant DL380)Two hot-swap supplies (1+1)One supply on A, one on B. Either can carry the server alone.
NVIDIA DGX B30012 supplies, N+NRuns at full capacity on six, so it can lose a whole feed.
NVIDIA DGX B2006 supplies, 5+1Keeps running on one feed with GPU power cut from 1,000 W to 800 W each.
NVIDIA DGX H100 and H2006 supplies, 4+2Runs at reduced performance on one feed.
Dell PowerEdge XE96806 supplies; 3+3 modeThrottles when one feed drops.
Switches and routersVaries by modelCheck each model; some access switches have a single supply.
Workstation and consumer-class hardwareUsually one supplyCan’t use A+B directly. An automatic transfer switch in the rack can feed it from both sides, but it becomes a single point of failure.
A small UPS inside the rackOne inputAvoid it in an A+B cabinet: it puts a single point of failure back in the path.

From NVIDIA’s and Dell’s system documentation. For GPU servers, ask how the system behaves on one feed before you size the circuits: some keep full performance, some slow down. Each feed circuit also has to carry every server on it.

Common A+B configurations by deployment size

The four rack sizes on our November 2026 price sheet, with the circuit each feed usually needs to carry the whole rack.

FootprintCircuit on each feed (A and B)Usable per feed$/month on our sheetTypical use
Half rack, 24U, 2 kW20A, 120V1.9 kW$750–1,500A few servers and a switch
Full rack, 48U, 5 kW30A, 208V5.0 kW$1,500–1,800Standard 1U–2U servers, storage
Full rack, 48U, 15 kW60A, 208V three-phase17.3 kW$4,500–6,750GPU inference, dense compute
Full rack, 48U, 30 kW60A, 415V three-phase34.5 kW$9,000–9,999GPU training racks; confirm cooling

Prices are the range across the markets on Bob’s City Price Sheet, November 2026, per cabinet per month with 100 Mbps–1 Gbps; A+B delivery and circuits vary by facility, so confirm both in the quote. Above 30 kW a rack, power and cooling are designed case by case, often with liquid cooling.

PDU types in A+B colocation setups

In an A+B cabinet you have two PDUs, one per feed. Their type decides what you can see and do remotely.

PDU typeWhat you getWhen it’s worth it
BasicOutlets and a breaker; no monitoring.Small, stable deployments where you don’t track power per server.
MeteredLive total load on each PDU.Most deployments: you can see whether A and B are balanced and how close each is to its limit.
Switched, outlet-meteredLoad per outlet, and remote on/off for each outlet.When nobody is on site: reboot a hung server without a remote-hands ticket, and see which server draws what.

When a quote says “PDUs included,” ask for the make and model, the number and type of outlets (C13/C19), the maximum amps per PDU, and whether per-outlet metering is included.

Facility-level vs cabinet-level A+B: the gap that matters

Ask “do you have A+B power?” and almost every facility says yes. The question that matters is whether independent A and B feeds reach your cabinet.

  1. Facility-level

    Two paths in the power room

    What it means

    The building has independent A and B utility feeds, UPS systems and generators.

    Watch for

    Distribution to some rows may come from one side only, common in older halls and legacy power designs.

  2. Cabinet-level

    Two paths to your rack

    What it means

    Your cabinet gets one circuit from the A side and one from the B side, independent all the way back to separate UPS systems and generators.

    Why it matters

    It’s what concurrent maintainability means for your servers, not just for the building.

  3. How to verify

    Ask about your cabinet, in writing

    Ask

    Are the A and B feeds to my cabinet from independent UPS systems and generators? Can I see the one-line diagram for that row?

    Put in the contract

    “Independent A and B feeds to Customer’s cabinet, each from a separate UPS and generator path,” not “redundant power.”

UPS and generator infrastructure behind A+B power

Three systems stand between a utility outage and your servers. Each needs its own answer for the A and the B side.

  1. UPS

    Bridges the gap

    What it does

    Carries the load from the moment the utility drops until the generators take over, and filters sags and spikes.

    Ask

    Is it N+1 on each side? How many minutes of battery at the current load (about five is typical), and lead-acid or lithium-ion?

  2. Transfer switch

    Moves the load

    What it does

    An automatic transfer switch starts the move to generator power within seconds of a utility failure; the UPS covers those seconds.

    Ask

    Does each side have its own transfer switch, and when were they last tested under load?

  3. Generators and fuel

    Carries the long outage

    What it does

    Runs the building until utility power is back, which can be days.

    Ask

    How many hours of fuel are on site (Uptime’s Tier standard requires at least 12), and what does the refueling contract guarantee? “We have generators” doesn’t answer it.

When A+B power is worth the cost and when it isn’t

A+B costs more because the facility reserves power and builds paths twice. For most production workloads it’s worth it; for some it isn’t.

WorkloadA+B?Why
Production with an uptime commitment to customersYesAny SLA you sign depends on your power path.
A single database or server with no standby elsewhereYesIt has no other way to survive a power event.
Systems in scope for SOC 2, HIPAA or PCI DSSUsuallyAuditors ask how power is made redundant. See compliance-ready colocation.
GPU inference that earns revenue by the hourUsuallyDowntime is lost revenue; check the servers’ power supply redundancy too. See high-density colocation.
Development, staging and testOften notPlanned maintenance windows are acceptable.
Workloads that fail over to another siteOften notRedundancy lives at the site level instead.
Archive and cold backupOften notThe data is the asset; the server can be restarted.

Adding A+B later is harder than specifying it up front: it needs a second circuit and PDU, every server re-cabled, and a B path that may not reach your row at all. Put it in the first quote.

What A+B power costs: real deals on our desk

Facilities price A+B differently: some include it in the cabinet price, some charge per circuit, and some bill the kW you reserve on both feeds. These are A/B deals and quotes from our own desk, with what each price includes.

DeploymentPower$/monthWhat it includesStatus
Texas, two 17 kW cabinetsA/B 60A, 208V three-phase per cabinet$8,170 ($240 per kW)Space and power; 24 months. 100 Mbps and a /28 brought the order to $8,469.Signed, September 2026
Washington, one 10 kW cabinetA+B$2,700 ($270 per kW)Space and power; 12 months. $3,096 with a 1 Gbps commit and PDUs.Signed, June 2026
Sacramento area, full 42U rackAbout 6 kW, A/B feeds$1,732.501 Gbps flat rate, a /29; 12 months; $1,000 setup.Quoted, August 2026
Colorado, half cabinetA/B 120V 20A, 16A maximum$899.30100 Mbps, a /29, five hours of remote hands; 12 months; $0 setup.Closed, September 2026

Customers and providers withheld. Note the Colorado contract: a 20A circuit with a 16A maximum is the 80% rule written into the order. Ask every provider whether A+B is in the cabinet price or billed per circuit, and whether power is billed on the kW you use or the capacity reserved on both feeds.

What we ask before an A+B facility makes your shortlist

We don’t take “A+B power available” at face value. When you need A+B, these are the questions we put to each provider.

QuestionWhy it matters
Do independent A and B feeds reach the cabinet type you need?Facility-level A+B isn’t enough.
Are A and B fed from separate UPS systems?Two outputs of one UPS fail together.
Are A and B backed by separate generators?One generator fault shouldn’t take both sides.
Is each feed sized for your full rack load?Split loads trip breakers when one side fails.
Which PDUs come with the cabinet?Metered at least; switched if you need remote reboots.
Will you share the one-line diagram?If your team wants to check the design before signing.

The answers go into the notes we send with your options, so you know what was confirmed before the quote, not after.

Why “A+B power: yes” on a quote sheet doesn’t settle it

Almost every quote has the checkbox. What it means varies by facility, and the difference only shows during a failure.

THE DIY WAY

You take the checkbox at face value

Some facilities run independent A and B paths to every cabinet. Others give you two PDUs from the same panel, which protects you from a PDU failure and nothing else.

THE DIY WAY

You split your load across both feeds

Two 30A circuits look like 10 kW. With redundancy, they give you 5 kW: each feed has to carry the whole rack if the other drops.

THE DIY WAY

You find out in the first outage

A shared UPS or generator behind both feeds stays invisible until it fails. By then you’re three years into the contract.

How it works

You send the specs. We find the options. You decide.

STEP 1

Send your requirements.

Tell us what you're deploying, where you want it, and when you need it. Send the specs you have; we'll help with the rest.

HardwareRacks & kWLocationStart date

Estimates are fine. No perfect RFP needed.

STEP 3

Take the next step. On your terms.

Like the options? Contact the providers directly. Need more detail? Call or email us. We're here to help, not push you.

  • Go directly to the providers you like
  • Ask us questions whenever you need

Get 2–4 qualified options in 48 hours

Free for buyers

Your price is the same as going direct.

Comparable prices by email

Review the options before deciding on a call.

Trusted service since 2004

5,000+ clients helped.

By clicking here, I state that I have read and understood the Terms and Conditions

Case studies

See how we helped teams secure colocation with the right power, pricing, and providers.

Leonard Roszkowski

CEO Elemental Energy Solutions

Problem: Needed to source ASIC servers domestically. Skeptical about working with a new organization.

What we did: Connected them to buyers, sellers, and infrastructure partners across deployments. Removed procurement and logistics overhead entirely.

Result: Rapid organizational growth in a short period. Now uses QuoteColo as an ongoing procurement interface across hardware and infrastructure.

Noel Frutasio

CEO FSN Services and Communications

Problem: Regularly needed colocation space across multiple US states and time zones. Difficult to navigate the market without deep industry knowledge.

What we did: Defined requirements in one meeting, then delivered proposals with multiple carrier and data center options across every target market.

Result: Placed in 4 cities. Contracts signed quickly. Multi-state colocation needs resolved through a single point of contact.

Tim Mandell

DC Mining / MDI Access

Problem: Needed reliable options for crypto mining containers and equipment, along with industry partners who could support real deployment requirements.

What we did: Connected the project with relevant mining infrastructure and equipment resources through the QuoteColo network, simplifying the search and evaluation process.

Result: Gained a clearer path to suitable mining infrastructure, equipment and industry contacts without having to source every option independently.

5,000+

Clients helped since 2004

No Cost

to Buyers

500+

Worldwide providers

Quotes

in 48 h

Frequently asked questions: A+B power colocation

What does A+B power mean in colocation?

A+B power means your cabinet receives two independent power feeds. The A feed and the B feed each have their own UPS, distribution path and generator backing, so a failure or maintenance on one side doesn’t interrupt the other. It only protects servers with two power supplies, one plugged into each feed, and only if each feed can carry the whole rack on its own.

What is usable kW per feed and how is it calculated?

Usable power is volts × amps × 0.8, because the electrical code limits continuous loads such as servers to 80% of the breaker rating. A 30A, 208V circuit gives about 5.0 kW; a 30A, 208V three-phase circuit about 8.6 kW; a 60A, 208V three-phase circuit about 17.3 kW. Ask the facility for usable kW per circuit in writing, not the breaker size.

Do my servers need dual power supplies for A+B power to work?

Yes. A server with one power supply can only plug into one feed, so it goes down when that feed fails. Most enterprise 1U and 2U servers ship with two hot-swap supplies; plug one into the A PDU and one into the B PDU. GPU servers differ: NVIDIA’s DGX B300 runs at full power on one feed, while a DGX B200 keeps running with its GPUs slowed. Check before you size the circuits.

What’s the difference between facility-level and cabinet-level A+B power?

Facility-level A+B means the building has independent A and B utility feeds, UPS systems and generators. Cabinet-level A+B means your specific cabinet gets one circuit from each side, independent all the way back. A facility can have the first without the second for some rows, so ask about your cabinet, not the building.

What should I ask a facility to verify its A+B power?

Ask whether the A and B feeds to your cabinet come from independent UPS systems and generators, whether each feed is sized for your full rack load, and which PDUs come with the cabinet. Ask for the one-line diagram for your row if your team wants to check the design, and write “independent A and B feeds to Customer’s cabinet” into the contract.

What is N+1 vs 2N power and which do I need?

N+1 means one more UPS module or generator than the load needs, so one can fail without losing capacity. 2N means two complete, independent systems, each able to carry the whole load. In Uptime Institute’s Tiers, Tier III is concurrently maintainable and Tier IV fault tolerant; both assume dual-corded equipment on A and B. Most business workloads are well served by Tier III with A+B to the cabinet.

Does A+B power cost more?

Usually, but facilities price it differently: some include it in the cabinet price, some charge per circuit, and some bill the capacity reserved on both feeds. On our desk, a Texas deal for two 17 kW cabinets on A/B 60A, 208V three-phase circuits was signed in September 2026 at $8,170 a month for space and power, $240 per kW. Ask how A+B is billed before comparing quotes.

Can I add A+B power after I’ve already deployed?

Sometimes. If a B path already reaches your cabinet, it takes a second circuit and PDU and re-cabling every server’s second power supply, usually as a scheduled remote-hands job. If your row is fed from one side only, a real B path may need facility work that isn’t possible where you are. It’s far easier to put A+B in the first quote.

How does QuoteColo check A+B power at the cabinet level?

We ask each provider whether independent A and B feeds reach the cabinet type you need, whether they come from separate UPS systems and generators, and whether each feed is sized for your full load. The answers go into the notes we send with your options, so you know what was confirmed before the quote.

Does QuoteColo charge for this matching?

No. You don’t pay us. Providers share their existing standard sales commission with QuoteColo, so there’s no added fee or markup on your provider quote.